- The roads open to traffic at 13:00 on Friday 27 November 2026. The time may change because of the weather.
- They are parts of two planned city roads in Seya Ward, the Mitsukyo-Shimosoyagi Line and the Seya-chinai Line (romanised by us; the city gives no English names). Yokohama City says the route will carry the shuttle buses between Mitsukyo Station on the Sotetsu Line and the Expo site.
- From about 11:00 to 12:00 the same day, the public can walk the road before it opens. No booking is needed and you can leave when you like. It may be cancelled in bad weather.
- The meeting point is a temporary site near the Futatsubashi-hokubu community hall (469-1 Futatsubashi-cho, Seya-ku). The opening ceremony from 10:00 is by invitation only.
- The roads have pavements and cycle lanes, and a new signalled junction.
- They were built as part of a land readjustment project in the Futatsubashi-hokubu area. Work began in January 2019.
Our take
These two roads were put on the city plan in December 1957. The land readjustment plan was set in 2015 and work started in 2019, so it has taken about 69 years from the line on the map to cars on the road. The opening falls about three and a half months before the Expo opens.
Another section of the Seya-chinai Line, in the Futatsubashi-chubu district, is still being built by the city’s Decarbonization and GREEN×EXPO Promotion Bureau. The release does not say when it will open or whether the shuttle route uses it.
In the association’s transport plan, Mitsukyo is about 4 km from the site, around 15 minutes by shuttle bus. It is one of the stations you can reach from Yokohama Station on the Sotetsu Line without changing. For anyone planning to take the shuttle from Mitsukyo, the opening date of that section is the next announcement to watch, we think.
Tips for visitors
- The public walk is from about 11:00 to 12:00 on Friday 27 November, near the Futatsubashi-hokubu community hall. No booking is needed.
- The roads open at 13:00 the same day. Check Yokohama City’s release before you go, as weather can change the plan.
- Distances and bus frequencies from all four stations are in our guide to getting to the Expo.
Our take
The two roads were first planned in December 1957, so they take about 69 years to open. From about 11:00 that day anyone can walk the new road without booking. One section of the Seya-chinai Line, in the Futatsubashi-chubu district, is still under construction.