“Put electrical equipment inside an Albatross? I thought, seriously?” That was the reaction of Yuki Hatanaka, who handled the electrical systems for Obayashi Mori Sora Mirai, on hearing the brief: use temporary construction materials, but make sure they don’t look temporary. Albatross is a rented scaffolding system that workers walk on at construction sites. In this pavilion, it forms the frame behind the timber outer wall.
The pavilion stands in the Urban GX Village at GREEN×EXPO 2027, which runs from 19 March to 26 September 2027 on the former Kamiseya Communication Facility in Yokohama.
Site equipment, normally removed once the job is done, becomes the frame
The columns and beams are made of earth-retaining steel. These are temporary steel members that brace the walls holding back soil when ground is excavated deeply, to stop collapses and subsidence. Once the building is finished, neither the scaffolding nor the retaining steel will be visible to visitors. Shutaro Nakamura, head of the site office (Manager, International Horticultural Expo Pavilion Construction Office, Yokohama Branch), explains that both are normally used only for a while on a construction site and are never used as structural or finishing materials in a building.
According to Shotaro Murata (Manager, Structural Design Department, Design Division), who planned the structure, Albatross scaffolding runs around the outside of the building to support the cladding, while inside, a structural frame of retaining steel and Albatross beam frames makes the building compliant with the Building Standards Act. Because the pavilion will be used for only about six months, Murata says, the team chose not to use the materials and methods of a permanent building, and instead to use as much rented, temporary site material as possible.
Using scaffolding as structure came with constraints. Albatross is assembled from members of fixed sizes, so the height and diameter of each block were tied to those units, Murata recalls. Nakamura’s first concerns were that a cylindrical form demands more precision than usual, and whether temporary materials could properly keep the rain out. Because timber panels go on the outside, the scaffolding joints were fitted to the millimetre.
Hatanaka (Expert, Building Services Design Department, Design Division) says that the plan to build the stump-like form from scaffolding and retaining steel also meant electrical systems for a building of a shape never handled before. By Hatanaka’s account, the cladding panels are arranged as polygons, which leaves gaps at the corners, so the line that keeps out rain sits on the inner wall side. The team has worked through issues like this one at a time, for example by making the equipment between the cladding and the inner wall waterproof.
Murata sees the pavilion as something “we are all still raising together”, with room to make it better. Yasuhiro Rikuno (Manager, Architectural Design Department, Design Division), who designed it, expects that even with the frame hidden, visitors will sense that something is different from the other pavilions.
Timber panels in varied colours and grain, to become site hoardings after the Expo
The cladding is made of timber panels called lamina panels. According to Murata, they follow the dimensions of construction-site hoardings: 2 or 3 metres high, in widths based on a 50-centimetre unit. A caption in the construction report notes that each panel differs in colour and pattern.
Expecting the panels to swell and shrink slightly when wet, Nakamura proposed to the designers that the gaps between them be made wider. Each time the drawings drifted out of line, they went back to the design team to be fixed, and this has happened again and again. Nakamura admits that with a temporary building used for a limited period, it is tempting to think it only has to last until the Expo ends. Even so, the site head says, “even if it is a temporary structure, I want to build something of real quality.”
According to Rikuno, the joints in the outer wall are sealed with tape that can be peeled off and reused, rather than with sealant. Nakamura adds that the members are not welded together either; the team uses parts already on the market so that the building is easy to take apart.
After the Expo, the panels are to be used at other sites. The construction report says the plan is to turn them into construction-site hoardings and similar uses. Murata says there is also an idea of rolling out timber hoarding panels across Obayashi’s construction sites, and the reception at this pavilion may be a test of that.
Rikuno explains that strip LED lights of the kind used on construction sites are fitted into the gaps between the panels, so that after dark the silhouette of a tree stump appears.
Chosen in an internal competition: a plan to open the construction site to visitors
The exhibit concept, “New Sustainable Life with MAKE BEYOND”, was settled by a group of about 20 mostly younger employees, gathered from across the company around October 2024, after about three months of discussion. Designs for the building were then sought in an internal design competition. It ran for about a month in February 2025; about 70 people took part and about 40 proposals came in. At judging around March, the top “Platinum” award went to the proposal by Hiroki Minoura (Manager, Osaka Architectural Design Department, Design Division).
Minoura’s idea was to open up to visitors the construction site that is usually closed off behind hoardings, and to make the building itself the exhibition space rather than a box for exhibits. The competition entry also included walls made with a 3D printer that would serve as signage and exhibits, guiding visitors through. According to Minoura, for reasons including the circular economy, printing those walls was not possible this time. Hitomi Kadono of the project team says the walls are being reconsidered in the form of timber hoardings.
The building is a row of cylindrical blocks of different sizes and heights, each shaped like a tree stump. Marco Capitanio (Assistant Manager, Design Solutions Department, Design Division), whose entry won the “Gold” award, took Minoura’s plan and designed the stump-shaped landscaping around it. In the architectural concept on its official site, Obayashi links the stump with its own image as a “pioneer” using wood to cut a path into the future.
According to Naoki Honda (Expert, Building Sales Department, Yokohama Branch), this is the first time Obayashi has put up its own pavilion at an international exposition.
A site with a high share of scaffolders and carpenters
Nakamura says that because of the unusual design using scaffolding and retaining steel as the frame, scaffolders (tobi) and carpenters make up a large share of the workforce, and they have been working on site for longer than on an ordinary building.
The site office is also a timber building, matching the pavilion’s cladding. It was moved here after being used at another site, and when the work is finished it is to be dismantled and used again elsewhere.
Mist built into “The brænch”, to be made with a metal 3D printer
Although the competition entry’s walls will not be 3D-printed, there is a separate structure, “The brænch”, designed by Capitanio. It is to be made with a metal 3D printer at Obayashi’s Technical Research Institute. Satoshi Yasuda of building services design explains that, as outdoor equipment, it will include “Saratto Mist”, which gives off a fine mist that does not wet you when it touches you. According to Rikuno, moving it to another site after the Expo is under consideration.
Completion planned for February 2027; the exhibits inside are not yet announced
Construction began in February 2026. The foundation work from February to April used Clean Crete, Obayashi’s low-carbon concrete in which most of the cement is replaced with industrial by-products such as ground granulated blast-furnace slag. In May and June the retaining-steel columns and beams went up, and scaffolding was assembled on top of the concrete around the perimeter. Fitting of the cladding panels began in July. As of the 31 July construction report, the next steps were interior and services work, then finishing the landscaping, including planting, around winter. Completion is planned for February 2027.
According to the official site, the interior is set in two worlds: the “Land of Forest” (Mori no Kuni), an ideal city living in harmony with nature, and the “Land of Sky” (Sora no Kuni), where life with space has become part of everyday life. The exhibits, admission charges, time needed and how to book had not been announced as of 2 November 2026.